Team 7 — Design Budget

Phase-based estimate aligned to a ~$5M project. Values include fees, disbursements, subs, and taxes.

Conceptual (sum)

Preliminary (sum)

Detailed (sum)

Grand Total (design)

of $5,000,000

Phase Breakdown

Cost Metric Conceptual Design Preliminary Design Detailed Design Sum
Team Hours 117 195 468 780
Team Total Costs
Normal Disbursements
Project-Specific Disbursements
Sub-consultants
Subcontractors
GST
PST
Phase Totals
Conceptual covers option screening and early coordination; Preliminary advances the preferred concept to feasibility; Detailed concentrates production, coordination with subs, permitting support, and tender documentation.

Construction Cost Model — Cable-Stayed (Concept)

Bridge Type Span (m) Deck Width (m) Deck Area (m²) Base Unit Cost ($/m²) Remote Factor Contingency Total Cost (CAD)
Cable-Stayed 125 4 500 $9,900 +15% +10% $6,261,750.00
Computation check: 500 m² × $9,900 = $4,950,000; +15% remote = $5,692,500; +10% contingency = $6,261,750.

Total Project Roll-up — Cable-Stayed

Metric Amount (CAD)
Estimated Construction Cost$4,641,252.02
Remote Site Premium (15%)$696,187.80
Construction Contingency (10%)$464,125.20
Total Design Fees$428,747.60
Estimated GST$311,515.63
Estimated PST$184,046.95
Total Cost (CAD) $6,725,875.21
Above roll-up pairs the construction base with remote premium & contingency, then adds design and taxes to give a whole-of-project planning figure.

Lifecycle Snapshot — Cable-Stayed

Item Value
Expected Life Cycle (years)75–100
Approx. Annual Maintenance Cost (%)0.4%
Approx. Annual Maintenance Cost (CAD)$26,903.50

Design Fee Breakdown — Cable-Stayed (towers + stays)

Role Hours Rate Cost
Project Manager (E5)80$299.00$23,920.00
Senior Engineers (E4)160$274.00$43,840.00
Project Engineers (E3)290$219.00$63,510.00
Technologists (T4/T5 avg)200$216.00$43,200.00
Admin50$80.00$4,000.00
Subtotal (fees)780$178,470.00
Disbursement Type Estimated Cost Markup To Client
Normal disbursements (8%)$14,277.60
Project-Specific Disbursements$50,000.0010.00%$55,000.00
Subconsultants (Geotech + Wind/Seismic)$120,000.005.00%$126,000.00
Subcontractors (Site prep, traffic, drilling)$50,000.0010.00%$55,000.00
Subtotal (fees + disbursements) $428,747.60
Tax Type Applied on Rate Cost
GSTFees + disbursements5.00%$21,437.38
PSTSoftware + Goods7.00%$10,000.00
Total design fee $460,184.98
Why higher than an arch: tower design, stay-cable forces, damping/aero serviceability, and staged construction.